Thursday, March 31, 2016

Wednesday, March 30, 2016

Tuesday, March 29, 2016

Wednesday, March 23, 2016

Update

Lightweight floors are being prepped and poured. 







3rd floor trusses are swung on part B. 






Thursday, March 10, 2016

Aluminum Storefronts

The aluminum storefront windows are nearly complete and we have begun installing the curtain wall. 










Update


Aluminum storefront windows are being installed. 

Tuesday, March 8, 2016

Insulation and Drywall

2nd floor is half done for insulation. 



Drywall is starting on 3rd floor. 



Monday, March 7, 2016

Insulation

On one and a half units left to insulate on 3rd floor we will start drywalling tomorrow. 











Friday, March 4, 2016

Update

Building B - trusses are prepped to swing today and tomorrow for the 2nd floor. 






Tuesday, March 1, 2016

Update



The floor trusses for 2nd floor will start arriving today. 


On 3rd floor we are starting insulation.