Wednesday, April 20, 2016

Busy Day On-site

The remaining roof trusses are being set on the 2 story potion of the building. 


The roofer are getting the building dried in. 


We are pouring lightweight concrete on 1st floor. 








Bio-ponds, black dirt and curbs are being prepped. 


Parisi is onsite to start running string line for curbs. 


Carpet is being laid on 3rd floor. 





Retaining walls are being poured. 











Monday, April 11, 2016

Update

2nd floor is painted out. We are starting accents and flooring. 



Windows for building B are being delivered and last truss truck is arriving for 3rd floor roof to swing Tuesday and Wednesady. 










Friday, April 8, 2016

Update

Kitchen cabinets are being set. 



Millwork is being installed. 


Part B - roof trusses are partially set and being sheathed. 





Tuesday, April 5, 2016

Update

2nd floor - drywall finish is nearly complete.
 



3rd floor - accent paint and hard surface flooring is complete
 


3rd floor cabinets and millwork is being delivered.
 
 
 
Roof trusses for building B are being delivered and spread to be swung tomorrow.
 

Friday, April 1, 2016

2nd Floor

We are pouring lightweight on 2nd floor. 




Wood floors

The wood floors are being installed and will be completed Monday. Monday the cabinets start getting installed and Tuesday trim arrives.