Wednesday, April 20, 2016

Busy Day On-site

The remaining roof trusses are being set on the 2 story potion of the building. 


The roofer are getting the building dried in. 


We are pouring lightweight concrete on 1st floor. 








Bio-ponds, black dirt and curbs are being prepped. 


Parisi is onsite to start running string line for curbs. 


Carpet is being laid on 3rd floor. 





Retaining walls are being poured. 