2nd floor - drywall finish is nearly complete.
 



3rd floor - accent paint and hard surface flooring is complete
 


3rd floor cabinets and millwork is being delivered.
 
 
 
Roof trusses for building B are being delivered and spread to be swung tomorrow.
 